It’s going to be a bureaucratic nightmare! Like shooting at a target in the dark
Bushfire considerations dominate all other considerations for design and rebuild
The process of rebuilding is expensive, stressful and arduous
Appreciation of requirements for rebuilding planning and permits, including time for actual process from start to finish
Information is available. Take it in steps. Approach authorities and get the answers you need in the order you need
It is going to take much longer to build than expected
Now I know the importance of the Concept Phase
New information about length of build time and the regulation challenges that will need to be met when rebuilding
A lot of detail and time required to rebuild
Planning consultants poor accreditation system in Victoria
Though I am familiar with many planning processes I have made notes about design priorities, the need for sealed buildings to have ventilation options & bushfire shelters for follow up
There are provisions for temporary dwellings
Length of planning process and complexity of planning overlays
Planning permit compliance expenses
How long it may take to rebuild and the importance of taking time over this
Some of the new requirements are relevant and can be improved on existing homes, e.g. fire truck access